What could a delay in contract performance potentially lead to?

Study for the CIPS Contract Administration (L3M3) Test. Master key concepts with our structured flashcards and multiple-choice questions. Each question includes hints and explanations. Get ready to excel in your exam!

A delay in contract performance can lead to the pursuit of contractual claims or disputes because delays often disrupt the agreed-upon timeline or scope of work, which can cause frustration and a breakdown in the relationship between the contracting parties. When one party fails to perform their obligations in a timely manner, the other party may feel compelled to seek recompense for any financial losses or damages incurred as a result of the delay. This situation usually involves claims for breach of contract or demands for renegotiation, which can escalate into formal disputes if not addressed amicably.

In contrast, increased trust and collaboration between parties (as suggested in the other options) might be ideals that can emerge from effectively managed situations, but they are less likely in instances of delays that lead to dissatisfaction and potential conflict. Therefore, delays primarily create a context for disputes rather than a positive environment for cooperation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy